EVG-3D Installation Process

Installation Processs of the EVG-3D Construction System - 8 Steps from start to finish

Step 5 - Shoring & Placing of Slabs

The EVG-3D panel system can be used for any roofs and floor slabs between storeys. Shoring is to be carried out using adjustable props with tripods and beams. Slab panels are reinforced with additional rebars at the bottom, U-bars at supports and splice mesh between panels. Slab panels are lifted manually and supported on the wall panels. This system could also be incorporated with traditional construction methods.

This is white text Installation Process - Step 5

Step 6 - Utilities

Another great feature of this system is the way it accommodates utilities. Once panels are secured in place, all services are passed between the reinforcing mesh and polystyrene. In order to increase this space, a propane torch or a heat gun may be used to melt the polystyrene.

Installation Process - Step 6